Setting up non-commercial clinical trials takes too long in the UK: findings from a prospective study.
To evaluate the specific components of setting up a simple multicentre clinical study four years after the new UK law on clinical trials was implemented in 2004. ⋯ While some centres can activate trials relatively quickly, there is considerable variation the time taken to set up a trial, much of which is due to the delay in obtaining R&D approval. This is having a major adverse effect on UK health research. There is a national need to streamline the process for considering multi-centre non-commercial clinical trials, in particular, having fixed timelines for R&D assessment. Without this, the costs of trials will increase because of extended duration, and the time to answer a research question and alter clinical practice will be significantly prolonged.